GP2013 R2-Needing to cancel a PO qty created off a Requisition

$
0
0

Hi Folks.  I'm on GP2013 R2.  I'm not using workflow. I'm not using the POP and SOP commitment functionality.   I've created a requisition and have converted that to a Purchase Order.   In the PO, I would now like to cancel the qty ordered but I receive a message saying that the line can't be cancelled as the remaining qty does not satisfy the commitmens for this line item.   Does anyone know how I can cancel the qty in the PO please?

Many thanks